What is the last step in releasing a lockout tagout?

Once the removal of Lockout Tagout Devices is done, the machine will be re-energized and restored to normal production operation.

5 Simple Steps to release / removal of Lockout and Tagout:
  1. Remove Tools and Replace Guards: …
  2. Check for Employees: …
  3. Notify the Affected Employees: …
  4. Remove Lockout Tagout Devices: …
  5. Restore Energy:

What are the 8 steps of lockout tagout?

The eight basic steps to a LOTO procedure are as follows:
  • Prepare for the shutdown. …
  • Notify affected employees. …
  • Shut down the equipment. …
  • Isolate energy sources. …
  • Apply LOTO devices to energy sources. …
  • Release/control all stored energy. …
  • Verify the lockout. …
  • Maintain the lockout.

What is the last step when performing a lockout/tagout procedure before you work on the machine or equipment?

Isolation Verification
Isolation Verification – This last step is about “making sure”.

What is the final step in returning equipment to service after a lockout?

Steps to follow after lockout/tagout could include:

Check the machine or equipment and the immediate area around the machine to ensure that nonessential items have been removed. 2. Confirm that all employees have been safely positioned or removed from the area. 3.

What are the basic steps of locking and tagging out a system?

What are the basic steps of locking and tagging out a system?
  • Prepare for Shutdown. …
  • Notify all Affected Personnel. …
  • Equipment Shutdown. …
  • Isolation of System (De-energization)